Peak to PeakBroomfield High School
Boulder Valley School District
Broomfield, Colorado

Client
Boulder Valley Public Schools
6500 Arapahoe, Boulder, CO  80301
Contact:  Bob Martin, Principal of Broomfield HS
(303) 466-7344

Architect
Anderson Mason Dale, P.C.
1615 17th St., Denver, CO  80202
Contact:  Doug Reisbeck  (303) 294-9448

Project Information
Use: High School
Type: Addition (primarily a 600-seat auditorium) and Remodel
Size: 14,000 SF Addition and
38,000 SF Heavy Remodel
Contract Amount: $4,500,000
Project Duration: October 1995 to Sept. 1996
Project Manager: Paul Sommer
Superintendent: Greg Thompson
Method of Delivery: Competitive Bid

Project Address
Broomfield High School
1000 Daphne
Broomfield, Colorado 80020

Description
The bidding was by prequalified, select listing.  The project was broken into five phases (to keep the building operational), with the primary auditorium addition built through the winter.  The auditorium work exposed us to several unique systems, including theatrical lighting, acoustic, sound reinforcement, and playback.  The remodel phases started as late as the end of the school year, and involved science laboratories, locker, class and music rooms.  One of the more interesting challenges was "popping up" part of the structure as part of an effort to increase circulation pathways.  Some of the building components used included caissons, helical piers, ground-faced block, brick, steel joists, built-up roofing, handicap lift, radial skylight, mechanical and electrical.